CYCA Redevelopment: C Arm Reconfiguration

Dear Members,

The commencement of the next phase of our redevelopment, the reconfiguration of C arm of the marina, has been delayed by approximately two weeks due to the extreme weather Sydney has experienced over the last week. Work will now begin on Thursday 28 June 2012 and scope of works will include:

• Disconnect the C arm gangway from the C arm deck
• Terminate the existing services
• Remove 3 existing piles
• Drive 1 pile to support the relocated walkway
• Relocate 3 existing marina figures
• Swing the C arm walkway 90 degrees to connect with the elbow of the B arm walkway
• Reconnect services
• Reconnect the existing C arm gangway alongside the A arm gangway
• Connect additional pontoons to increase the entrance area of the marina at the base of A arm gangway

The program of works shows the reconfiguration will take around 3 weeks and cause minimal disruption to berth holders located on C arm. The last 2 activities of the scope of works will likely occur after the overall reconfiguration takes please.

We plan to keep the pond open while the works are taking place, however some disruptions or possible pond closures might occur subject to the operation of the barge that will be established during the first week of the program.

At the conclusion of the work, the only entrance to the marina will be via the existing A arm gangway, which we hope will become a focal point of the Club’s operations.

I wish to pass on my thanks for the ongoing work being conducted by the Redevelopment Committee and ask for your ongoing co-operation and patience while this phase of the development is carried out.

Garry Linacre
Commodore